监理细则电气工程

来源:伴沃教育
佳和人家

(电气工程)

监 理 实 施 细 则

编 制:

审 核:

XXXXXXXXX 2015年10月30日

目 录

一、工程概况:

1.工程名称················································· 2.工程地点················································· 3.建设单位················································· 4.设计单位················································· 5.施工单位················································· 6.工程概述················································· 7.电气主要指标·············································· 8. 供电电源与电压及保护接地···································· 9.导线选择及敷设方式········································ 10.电气设备安装············································· 11.防雷与接地··············································· 12.等电位接地··············································· 13.节能····················································· 14.剩余电流式电气火灾报警系统······························· 二、监理工作流程:

1、施工前检查要求··········································· 2、检查验收程序和要求······································· 3、 材料抽样及检验··········································· 三、电气安装工程监理细则:

一)电缆线路的敷设·········································· 二)配管及管内穿线·········································· 三)电气照明器具及其配电箱(盘)安装工程······················ 四)成套配电柜(盘)及动务开关柜安装·························· 五)电机的电气检查与接线···································· 六)避雷针(网)及接地装置安装工程···························· 七)电气工程竣工验收资料····································

一、 工程概况及特点

1、项目名称:XXXXXXXXX 2、建设地址:XXXXXXXXX 3、建设单位:XXXXXXXXX 4、设计单位:XXXXXXXXX 5、勘察单位:厦门地质工程勘察院 6、施工单位:XXXXXXXXX

7.1本工程建筑面积88681.83m³,该工程各楼室内外高差、层数建筑物高度(室外地面至屋面板板顶),设计标高±0.000相当于绝对标高(黄海高程),上部结构体系分别为(各楼平面位置如下图所示); 楼号 室内外高差(mm) 1#2# 详建施 2 31 99.800 地下室楼层 地面以建筑物±0.000相当于绝对高度(m) 149.000 首层楼面板 3# 详建施 1 5 22.400 149.000 首层楼面板 中部裙楼部分 开闭所部分 详建施 2 5 10.800 149.000 详建施 2 5 23.400 149.000 首层楼面板 首层楼面板 框架结构 框架结构 框架剪力墙结构 框架结构 嵌固部位 上部结构体系 上楼层 高度(m) 7.2本工程在一类、二(a)、二(b)类环境中的结构设计使用年限为50年。 7.3计量单位(除注明外):1)长度;mm;2)角度; 度;3)标高:m;4)强度:n/mm³。

7.4建筑物应按建筑图中注明的使用功能,未经技术鉴定或设计许可,不得改变结构的用途和使用环境。

7.5凡预留洞、预埋件应严格按照结构图并配合其他工种图纸进行施工,未经结构专业许可严禁擅自留洞或事后凿洞。

7.6结构施工图中除特别注明外,均以本总说明为准。

7.7本工程各楼层梁及屋面采用“平方表示”,其制图规则详《混凝土结构施工图平面整体表示方法制图规则和结构详图》11G101-1与12G101-4. 8.电气主要指标:

本工程为为一类高层综合楼,电源引自一层变配电所2台1250kVA变压器,地下室附设400kW柴油发电机,供电电压380/220V, 三相四线制;应急照明、消防电梯、加压送风机等消防负荷为一级负荷,采用双电源供电,一用一备最末端自动切换; 普通客梯、生活水泵、排污泵负荷为一级负荷,采用双电源供电;其余为三级负荷. 主供电源由一层变配电所正常母线段引来,备供电源由一层变配电所应急母线段引来。

8.1.供电电源与电压及保护接地:

本工程采用TN-S接地保护方式,电源进线的PE线做重复接地。 9.导线选择及敷设方式:

9.1.照明电源由各层电表箱引入,线路为WDZ-BYJ-2.5mm2穿PC16/20暗敷; 9.2.应急照明线路采用WDZN-BYJ-2.5mm2穿SC15/SC20管于墙与顶板内暗敷; 9.3.电力干线采用插接式母线槽及BBTRZ- 、WDZ-YJY-、YJY22交联电力电缆,由一层变配电所引出至各层电表箱,电管井在线路施工完毕后均应采用经国家有关部门鉴定的防火堵料封堵, 所有与消防设备有关的线路均穿金属管或封闭式金属线槽敷设,暗敷时敷设在楼板及墙体内,且保护层厚度大于30mm,若明敷时应刷防火涂料处理。

9.4. 在强电井内的电力电缆采用防火保护的封闭式金属桥架敷设, 弱电井内的

弱电线路采用防火保护的封闭式金属桥架敷设,待电气管线安装完毕后,每层电井均需做防火密闭封堵。

9.5. 一般照明,动力线路明敷时应采用阻燃低烟无卤聚乙烯绝缘电缆电线; 9.6. 当消防负荷与非消防负荷在电缆桥架内敷设时,需要与非消防负荷采取防火隔离处理,消防用电设备应设有明显标志,其面板上应要求开关柜生产厂家标注\"消防用电\"等红色字样的明显标志; 10.电气设备安装:

10.1配电间内配电箱、电梯电源箱、控制箱挂墙明装,其余配电箱嵌墙暗装。配电箱、控制箱箱底距地1.5m安装。动力柜落地安装,室内落地式配电柜底部抬高,高出地面100mm,底座周围应采取封闭措施。;

10.2.室内开关暗装距地 1.1m,,普通暗插座距地 0.4m,柜式空调用插座距地1.5m,卫生间暗装插座距地0.8m,残卫求助呼叫按钮距地 0.5m,残卫求助呼叫电铃距地2.2m。

10.3.电梯井道内设电气照明,距井道最高点和最低点 0.5m内及井道中间每隔 5m各设一盏灯;

10.4.电气强弱电竖井内设-40x4热镀锌扁钢,上下贯通,下端与总等电位联结端子箱联结,电气强弱电竖井内的接地干线应与每层楼板钢筋作等电位联结; 10.5. 金属线槽及电缆桥架敷设时;全长不少与两处与接地干线连接。 10.6. 应急照明灯吸顶安装,安全出口灯及层显灯底边距地2.2米安装,疏散指示灯底边距地0.3米安装,自带蓄电池的备供时间不得小于30分钟.应急照明灯,安全出口灯,层显灯, 疏散指示灯应设玻璃或其他不燃烧材料制作的保护罩, (设备用房的备用照明不低于正常照明照度,且供电时间不得小于180分钟);

11.防雷与接地:

11.1.经计算,本综合楼年预计雷击次数为0.3442,大于0.25次/a,故本工程按二类防雷设计;

11.2.建筑物设接闪器保护;接闪器与支架用∅12mm热镀锌圆钢敷设在屋顶沿女儿墙与楼梯顶及屋脊上.支架全长0.20m,埋深0.1m,水平间距1.0m,转角处0.5m,接闪器与引下线焊接长度不小于100mm.周边敷设的接闪带,接闪带设在外墙外表面或屋檐边垂直面上;

11.3.防侧击雷和等电位措施: 对水平突出外墙的物体,当滚球半径60m球体从屋顶周边接闪带外向地面垂直下降接触到突出外墙的物体时,应采取相应的防雷措施,在建筑物上部占高度20%并超过60m的部位,各表面上的尖物,墙角,边缘,设备以及显著突出的物体,应按屋顶的保护措施处理,在建筑物上部占高度20%并超过60m的部位,布置接闪器应符合对本类防雷建筑物的要求,接闪器应重点布置在墙角,边缘和显著突出的物体上;外墙内,外竖直敷设的金属管道及金属物的顶端和底端,应与防雷装置等电位连接;

11.4.引下线:利用全部混凝土柱内两根主钢筋(每根不小于 ∅16mm)焊接作引下线, 其接点应焊接成可靠的电气通路.各引下线在一层室内距地坪 0.8m处做暗装测试卡,以便测试接地电阻;

11.5.防闪电电涌侵入措施:将进入建筑物的各种管线均埋地下引入, 并在入户处将电缆金属外皮,钢管等与接地装置连接;

11.6.接地极:利用建筑结构作接地装置;引下线钢筋与地基梁内钢筋可靠焊接构成电气通路;

12.7.接地电阻:防雷,重复接地,PE线等接地共用时实测接地电阻不大于 1欧姆,

若达不到此值,须另增打接地极; 12.等电位接地:

12.1.总等电位接地;在电源总进线箱下距地0.3m处设置总等电位端子箱, 并与下列可导电部分互相连通,PE,PEN干线,所有进出建筑物的金属管道及构件, 电气装置接地极,接地干线,条件许可的建筑物金属构件等导电体.为此,须在强弱电气竖井内设置-40X4镀锌扁钢接地干线,与总等电位端子箱相连;

12.2.局部等电位接地:在卫生间洗脸台下及电梯机房,风机房距地 300mm处安装JFG-II型(75x75x60mm)等电位联结端子箱并与水管.楼板及混凝土柱内钢筋焊接;

12.3.总等电位联结端子箱相连.施工参见国标图集<<等电位联结安装>>(02D501-2) 在电梯机房内四周离地300明敷一圈热镀锌扁钢.过门处改为地下暗敷; 13.节能:

13.1.电梯控制装置采变频器控制,可节电30%~60%;

13.2. 公共部分照明灯具采用节能灯及三基色T5系列荧光灯;荧光灯带电子镇流器(功率因数0.95以上) 以提高照明效率;楼梯间照明采用声控延时开关防止长明灯;达到节能的目的; 14.剩余电流式电气火灾报警系统:

14.1.漏电火灾报警系统由剩余电流火灾监控探测器;电气火灾监控设备等组成; 14.2.系统要求:探测漏电电流;过电流的信号,发出声光报警,报出故障线路地址,并可切除漏电线路上的非消防电源,消防设备电源在达到设计漏电值时在主机处报警,但不能动作于跳闸.能储存各种故障和操作试验信号,信号存储时间不应少

于12个月;

14.3.漏电火灾报警系统信号送入消防控制室。

二、监理工作流程:

1、施工前检查和要求

1)施工单位应向监理机构提交施工许可证、营业执照和资质证书。

2)施工单位应在开工前提前二周向监理机构提交经公司审批并有总工程师签认的“施工组织设计”、监理机构应在开工前审核并签署监理意见。 3)监理机构根据“施工组织设计”提供的施工人员名单进行检查确认,内容为:

1项目经理及主要管理人员、技术人员的上岗证。 ○

③专职质检员、测量员、施工电、安全员上岗证。

③特种工种上岗证:电焊工、电工、机械操作工等人电一岗证,均需附身份证复印件。

④须设专职安全员二名及现场文明施工管理员二名,佩戴袖章上岗。 4)监理机构成根据“施工组织设计”中编制的总进度计划,检查、确认满足开工条件所需的工程原材料、构配优点的数量及质量。

5)施工所需机械设备的检查确认,按施工组织设计中所提供的施工机械设备一览表及到场时间进行,施工机械设备监理均需检查:选型情况,主要性能参数和使用操作要求等内容。

6)根据施工方法,检验方法的质量控制要求。施工单位提交下列施工要求: ①工序检验利隐敝工程验收报表。

②进场原材料、构配件等的数量、规格、进场时间,拟使用部位和使用情况的报表。

③进场施工机械设备的名称、型号、主要性能参数,操作使用要求及大型设

备的检验证书等情况报表,应注明进场时间及使用期限。

④信息管理用表,包括签证单、工作联系单、技术核定单等一系列信息管理用表。

⑤监理要督促施工单位按档案管理要求进行资料管理工作,资料应全面、正确、及时。

7)须经总监理工程师签发“开工报告”后方可正式施工,签发开工报告,除本

节前述检查的内容外,还须:

①审核施工单位的质量保证体系,安全生产保证体系,质量管理制度,安全

生产管理制度和职能分工的落实情况。 ②审核施工单位的施工现场平面布置图。

③检查施工人员的到位情况,水电布置情况、临时设施情况、测量控制点的布设情况等。

2、检查验收程序和要求

1)施工单位自检包括施工班组自检、互检(下道工序检查上道工序)、专职质检员检验(分包单位先检验,总包单位后检验)。施工单位质检员自检合格后,须经项目质量技术负责人签字认可。

2)监理验收:监理工程师收到签证单,经审核无误后,一般情况下应尽快进行验收,最迟不超过24小时。

①经验收合格签字认可后,才能进入下道工序施工,验收不合格,监理应在验

收单上写整改要求,并留下验收单存档,施工单位必须进行认真整改或返工。 ②整改或返工后,再进行自检程序,自检合格后,按验收程序报监理工程师复验。

③如复验仍未通过,施工单位应查明原因,进行内部整顿和调整,一般再24小时内,由施工单位负责人向监理机构提交书面报告,总结经验教训并落实具体措施。

④施工单位未自检或自检无质检员和技术负责人签字,监理工程师可拒绝验收。

3)监理工程师在施工过程中发现的质量问题,应及时以口头和书面方式通知施工单位立即纠正,同时做好监理日记的记录。

①对于监理工程师提出的质量问题,施工单位没有及时纠正,验收时发现必须返工重来。

②施工单位应加强成品保护的检查,并追究有关人员的责任,发现的问题,及时处理。

4)分项和分部工程完成后,施工单位应分期,分层立即进行分项和分部工程质量检验评定,并填表,评定等级及签名后报监理备案。

3、材料抽样及检验

1)用于工程的主要材料和产品进场时,必须同时向监理提交正式的进场材料合

格证和试验报告单进行核查。进口材料必须提供商检部门的检验报告。 ①材料和产品进场后及材料加工过中抽样,必须由业主、施工、监理三方(或

施工、:监理理二方)共同分期、分批、分规格进行抽样,送具有测试报告资质证书的法定试验单位进行试验。“三无”主产品不得进入施工现场。 ②试验报告应及时送监理核查,经试验合格的材料的产品及加工件才能使

用;不合格一律不得用于工程,并不得存放在施工现场,必须在监理通知的期限肉撤离现场。

③单方抽检无效;非经法定试验单位的试验结果无效。

④监理对质量保证资料有怀疑或怀疑材料和产品质量有问题时,监理亦可随

时抽检,施工单位必须积极配合。

⑤施工单位应在使用材料前的一定期限内向监理机构报送有关材料试验报

告。监理工程师如发现有疑问时,应及时向施工单位提出意见,施工单位必须作出解释和处理。

2)建筑材料应在自检合格的基础上填写“材料设备进场使用报验单”,定期或不定期地报监理机构。

三、电气安装工程监理细则:

一)电缆线路的敷设

(1)、电缆敷设前,必须检查其型号、规格、电压等级,合格证及出厂技术文件是否符合设计要求。

(2)电缆的耐压试验结果,泄露电流和绝缘电阻必须符合施工规范规定。具体见新标准“GB50150-91”第十一章。工程中最常规的检查方法是测量电缆线间、线对地的绝妙电阻,对于100-1000V电缆,要求使用500-1000V兆欧表检测;对1000V以上的电缆要求用2500V兆欧表检测,绝缘电阻最低要求,见下表。低压电缆仅作绝缘测试,高压电缆除要作绝缘测试个,施工完毕后必须作耐压试验。

粘性油浸纸和滴油浸纸绝缘电阻

额定电压(KV) 最低绝缘电阻(MΩ) 0.1~1 100 6及以上 200 额定电压6KV以下的橡皮绝缘电缆

电缆截面(mm) 最低绝缘电阻(MΩ) 250及以下 50 塑料电缆

70-85 35 240 20 电缆额定电压 聚氯乙烯电缆 最低绝缘电阻(MΩ) 聚乙烯电缆 交联乙烯电缆 3、电缆敷设应满足以下要求:

1 40 - - 6 60 1000 1000 10 - 1200 1200 35 - 3000 3000 ①严禁有绞拧、铠装压扁,护层裂和表面严重划伤等缺陷。直进敷设时,严禁在管道上面或下面平行敷设。

②直埋电缆验收时,应检检查其挖路径、开挖深度、回填质量、电缆保护措施、电缆余量以及缆间、电缆与底下管道间平行交叉最小净距是否符合设计施工规范规定。隐蔽工程记录及简齐全、准确。

③坐标标高正确、排列整齐、标志桩、标志牌设置准确:有防燃、隔热和防腐要求的保护措施完整。对于进入建筑物的预埋套管按防水要求验收。 ④在支架缴设时,固定可靠,同一侧支架上的排列顺序正确。控制电缆应放在电力电缆的下面,

1KV及其以下的电力电缆应放在1KV以上电缆的下面。采用观察检查和检查隐蔽记录,按下同敷设方式各抽查5处。

4、电缆终端头和电缆接头的制作、安装必须符合下列规定:

①封闭严密,填料灌注饱满,无气泡,渗油现象,芯线连接紧密,绝缘带包

扎紧密,防潮涂刷均匀,封锚表面光滑,无砂眼和裂纹。

②交流聚氯乙烯电缆头的导体带,屏敞带包缠不超越应力集中锥中间最大处,

锥体坡度匀称,表面光滑。

③电缆头安装,固定可靠,相序正确,直埋电缆头保护措施完整,标志准确清晰。

④中间接头的设置位置应避免在道路交叉处、与管交叉处,建筑物大门口及相邻电缆接头处。

采用观察检查和检查安装记录的方式验收,不同类型的电缆头各抽查10%,但不少于5个。

5、电缆支、托架安装位置正确,连接可靠,固定可靠,油漆完整,在转弯处能托在电缆平滑均匀的过渡,托架和盖板齐全。采用桥架敷设时,应检查桥架位置,拼装、零部件的搭配、型号、规格、盖板等是否符合施工图与产品技术要求,施工中应注意与土建的配合。采用观察检查,不同的支、 托架各抽查5段。

6、电缆保护管安装管口光滑,无毛刺,固定可靠,防腐良好。弯曲无弯曲现象,其弯曲半径不小于允许弯曲半径,出入地沟、隧道和建筑物的保护管口封闭严密。采用观察检查,按不同敷设方式、场所各抽查5处。 7、明设成排支架相互间允许偏差lOmm。

8、渍漫电力电缆最小弯曲半径:单芯为不小于20d,多芯为不小于15d。 塑料电力电缆、控制电缆最小弯曲半径为不小于lOd。

塑料电力电缆最小弯曲半径;橡皮或聚氯乙烯护套不小于lOd,裸铅护套为

不小于15d,铅护套钢带装不小于20d。

9、电缆及其支、托架(含桥架)和保护管接地(接零):支线敷设连接紧密牢固,接地(接零)线截面选用正确,需防腐的部分涂漆均匀无遗漏。采用观察检查,抽查5处。 二)配管及管内穿线

l、导线的品种、规格、质量必须符合要求和国家标准的规定,漆的截面、长度可按生产厂标与合

同条款验收,一般应高于国家标准的规定。导线间和导线对地绝缘电阻标准大于.5兆欧。

2、薄壁钢管严禁熔焊连接,厚壁钢管可采用套管熔焊来连接。非熔焊接连接的钢管均需跨线连接,

管、盒连接处也应焊跨接线。采用塑料时应检查材质与施工场所是否符合设计与规范要求,施工时应加强保护与检查措施,对损坏的应及时修复,以确保施工质量。

3、管咱敷设要达到以下要求:

①连接紧密、管口光滑,护口齐全;明配管及其支架平直牢固,排列整齐,油漆防腐完整。吊顶内线管应按明敷要求验收,应单独设置吊筋。照明管宜采用钢管,也可采用阻燃性硬质塑料管,严禁采用塑料波纹管。消防管必须采用钢管,外刷防火涂料,连接采用金属软管时,应用金属接头。明配管保护层大于15mm,除埋入砼内的钢管外壁不作防腐处理外,其余地方敷设的钢管均需作防腐处理。 ②盒(箱)设置正确,固定可靠,管子进入盒(箱)内露出的长度小于5mm,用锁紧螺母(纳子)固定的管操扣,管子露出锁螺母的螺纹为2-4扣。 ③预埋线管时应注意与土建的配合,不得任意切断梁、柱、核心井筒的主筋,不可避免时应征得土建同意,采取加强补救措施,为了避免超越砼保护层厚度,过粱管要求从梁下走,核对管数量、路径时,建议依设回路走为宜。验收管径大小时,除核对设计图上明显标的外,重点注意核对仅仅标注穿线根数的管径是否与设计说明符合。为了美观及施工方便,与灯头盒连接的管子不宜超过四根,否则可增加接线盒。验收采用观察检查和检查隐敝工程记录,全数检查。 4、穿过变形缝处应有补偿装置,补偿装置能活动自如:穿过建筑物和设备基础处加套保护管。验收采用观察知和检查隐蔽工程记录的方式,全数检查。 5、管内穿线应达到以下要求:

①穿线前应检查管口有无毛刺,管内有无积水、杂物等,待一切处理完后方可穿线。穿线接头不得放在管内,严格安排在接线盒、灯头等处,接头做法应符合操作规程要求。

②在盒(箱)内导线有适当余量,不进入盒(箱)的垂直管子的上口穿线后密封处理好:导线连接

牢固,包扎严密,绝缘良好,不伤芯线。验收时采用观察检查或检查安装记录,抽查10处。

6、金属电线保护管、盒(箱)及支架接地(接零)支架敷设应连接紧密、牢同,接地(接零)线面正确,需防护的部分涂漆均匀无遗漏。

7、暗配管的最小弯曲半径不小乇6D。明配管的弯曲半径有1个弯时,不小于4D;有2个弯及以上时,不小于6D。管子的弯曲度不入于0.1D。明配管固定间距允许偏差:直径15—20mm时,为30mm;直径25—30mm时,为40mm;直径40—50mm时,为50mm;直径65-100mm时,为60mm。验收时采用尺量检查,按不同部位抽

查10处(每处1点)。

8、明配管水平,垂直敷设任意2m段内平直度、垂直度允许偏差3mm。 7、8)采用拉线、尺量检查,按不同部位、内容各抽查10处(每处l点)。 三)电气照明器具及其配电箱(盘)安装工程

l、1—3Kg以上灯具和吊扇应预埋吊钩或螺栓;预埋件须埋设可靠软线吊灯限于lkg以下,超过者应加吊连接或用钢管来吊灯具,吊扇要有防蚀设施,扇叶距地高度不应低于2.5mm。

2、所有需接地或接零的灯具、插座、开关、配电箱等的金属外壳,应由接地螺栓连接。配电箱金属外壳,厚度大于1.5mm,接地应有明显接地标志。 3、各种电气设备的规格,重要元器件应有合格证或质保书。配电箱内零线经汇流连接,回路编号齐全、正确。

4、螺栓连接时同一端子上导线不超过两根。开关切断相、灯头、插座相线位置正确。插座接地线须单独敷设,不与各零线混用。 5、漏电保护器必须测试。

6、配电箱、盘、板安装垂直度:成排灯具中心线;插座、开关安装高差需符合验评标准要求。

a)、总配电箱至分配电箱,分配电箱各回路的导线间,导线至地的绝缘电阻必须符合要求。监理应现场检测或实测。

b)、检测插座、开关灯具等标高是否符合要求,监理应在核实数量与观查的基础上,采用直尺、水准仪等抽查。

c)、开关是否断相线,插座零、相、地线接线是否正确,监理应用电笔、专用检验插头等工具检验。

d)、检查开关接通、断开位置是否统一,动作是否可靠。

e)、检查成排灯具中心线、间隔距离、标高是否符合要求,排列是否整齐、美观。检查方法是在

目测的基础上,用水准仪、直尺测量。 四)成套配电柜(盘)及动务开关柜安装 l、现场验收:

现场验收应同业主、承包商、监理三方共同进行,合格后三方签字生效,验收

内容:

①出厂合格证、试验记录、说明书等出厂文件足否齐全。 ②设备铬牌、型号、规格与设计是否相符。

③清点仪表、开关、继电器等元器,并检查其完好性,做好验收记录。 ④外观质量检查,初步检查柜(盘)的每米垂直度、盘项、盘面的平直度以及盘面接缝是否符合产品质量及安装规范要求。

2、成套配电柜(盘)与动力开关柜的试验,参照GB50150—91“电气设备交接试验标准”中的7-20章有关条款,验收方法,依审查试验记录为主,监理人员应经常到现场察看,检查,以核实试验记录的准确性。

3、柜(盘)的调整结果必须符合施工规范设计要求,调试时应切断柜(盘)的所有负荷,根据图纸逐一调整,检查动作顺序、动作时间、继电保护、起动要求是否满足设计。对重要的继电保护安装完毕后应重新标定,根据标定值对继电器保护进行整定,以满足送电与设备试车要求。盘(柜)送电后应按规定做好各项电气数据记录,验收方法为现场调试,现场验收。

4、柜(盘)上的高压瓷件要重点保护,表面严禁有裂纹,缺陷和瓷釉损坏等缺陷,低压绝缘部件必须完整,验收方法为观察检查。检查数量为全数检查。 5、柜(盘)内设备的导电接触面与外部母线连接必须紧密,用O.05×lOmm塞尺检查:线接触的塞不进去;面接触的,接触面宽50mm及其以下时,塞入深度不大于4mm;接触面宽60mm及其以上时,塞入深度不大于6mm,检查方法为现场实测,不同类型抽查1-3台。

6、柜(盘)组立应满足下列要求:

①柜(盘)与基础型钢连接紧密,固定牢靠,柜(盘)间接缝平整。 ②盘面标志牌、标杨框齐全、正确并清晰。

③小车、抽屉柜推拉灵活,无卡阻现象:接触触头接触紧必,调整正确,投入时接地触头比主触头先接触退出时接地触头比主触头后脱开。

④小车、抽屉式柜,动、静触头中心线调整一致,接触紧密,二次回路的切换接头或机械,电气联锁装置的动作正确可靠。

⑤小车、抽屉式柜的互换性好,特别是相同用途,相同类型、规格的小车、抽屉式柜要求能够互换。如两路进线时进线柜之间只能,出线柜之间以及容量相同

的电动机之间要求能够互换。

7、柜(盘)内的设备及接线应满足下列要求: ①完整齐全,固定可靠,操作部分灵活准确。

②有两个电源的柜(盘)母线相序排列对称,母线色标正确。

③二次接线准确,固定牢靠,导线与电器或端子排的连接紧密,标志清晰齐全。 ④二次接线排列整齐,回路编号清晰、齐全,采用标准端子头编号,每个端子螺丝上接线不超过两根。柜(盘)的引入,引出线整齐。

6、7检查方法都是现场观察,单独安装时抽查1-5台,成排安装的抽查1-3排。

8、柜(盘)及支架接地(接零)支线敷设应连接紧密、牢固,接地(接零)线选用正确,需防腐的部分涂漆均匀无遗漏。采用观察检查,抽查3处。

9、基础型钢安装允许偏差为:顶部、侧面平直度l‰,全长不超过5mm,需要注意的是若土建施工,电气监理人员应交待安装施工规范要求,并与士建监理人员共同验收。

10、柜安装允许偏差为:垂直度2‰,盘顶平直度,相邻两盘为2mm,成排盘面为5mm,盘面平整度,相邻两盘为1mm,成排盘面为5m,盘间接缝为2mm。 9、10验收皆为现场实测,采用工具为拉线、直尺、塞尺等,检查数量皆为不同类型抽查5处,值得指出的是基础安装高度问题,土建图上往往标的是结构高度,实际操作验收时按建筑高度来验收,一盘为顶部高出抹平地面10mm(手车式柜与地面平)为宜。 五)电机的电气检查与接线

1、电机型号、规格、质量必须符合要求。电机的试验调整必须符合施工的规范规定。试验调整参照GB50150-91的“电气设备交接试验标准”第2-5章的要求验收。重点为笫五章交流电动机部分,其投入运行前必须测量线的绝缘电阻,额定电压1000伏以下者,常温下绝缘电阻.额定电压1000伏及以下者,在接近运行温度时绝缘电阻值,定字线圈应不低于每千伏1兆欧,转子线圈应不低。于每千伏O.5兆欧。

2、电机接地端子与导线端子必须连接紧密,不受外力,连接用紧固件的锁紧装置完整齐全。在电机接线盒内裸露的不同相的导线间和导线对地间最小距离必须

符合施工规范规定。

3、电机安装前应按施工规范要求检查,当电机有下列情况之一时,应进行抽芯检查:

①出厂日期超过制造厂保证期限者。 ②经外观检查或电气试验,质量可疑时。 ③开启式电机经端部检查可疑者。 ④试运行进有异常情况者。 4、电机抽芯检查应达到下列情况:

①线圈绝缘层完好,无伤痕,绑线牢靠,槽楔无断裂,不松动,引线焊接牢固,内部清洁,通风孔道无堵塞。

②轴承工作面光滑清洁,无裂纹或锈蚀,注油(脂)的型号、规格和数量正确,转子平衡块紧固,

平衡螺丝锁紧,风扇叶片无裂纹:验收时抽查抽芯电机的30%,但不少于5台。重点检查大容量电机。采用观察检查或检查电机抽芯两种方式。 5、电机电刷安装应达到以下要求:

①电刷与换向器或集电环接触良好,在刷握内能上、下活动,电刷的电压正常,引线与刷架连接紧密可靠。

②饶线式电机的电刷抬起装置动作可靠,短路刀片接触良好,动作方向与标志一致。运行时电刷无明显火花。采用观察和试运行检查,抽查5台。

6、电机外壳接地(接零)支线应达到连接紧密、牢固,接地(接零)线截面选用正确,需防腐的部分突起均匀无遗漏。验收时观察检查,抽查5处。

①总配电箱至各分配电箱,分配电箱各回路的导线间,导线对地的绝缘电阻必须符合要求。监理应现场监测或实测。

②检查插座、开关、灯具等标高是否与图纸设计符合,监理应在核对数量观察检查的基础上,采用直尺、水准仪等抽查。

③开关是否断相线,插座左零、右相、地接线是否正确,监理应用电笔、专用检检验插头等工具核验。

④检查开头接通、断开位置是否统一,动作是否可靠。

⑤检查成排灯具中心线,间隔距离、标高是否符合要求,排列是否整齐、美观。

检查方法是在目测的基础上,用水准仪、直尺测量。 六)避雷针(网)及接地装置安装工程

1、总体要求:所有须接地装置连接后成为一个整体。(指联合接地系统)。 2、对接地装置安装工程所使用材料的有关规定: 扁钢厚度≥4mm,圆钢直径≥8mm。 3、连接要求:

①接地装置的接地电阻值必须符合设计1欧姆以下要求。监理应实测或检测接地电阻测试记录。检查数量为全数检查。

③接至电气设备、器具和可拆卸的其非带电金属部件接地(接零)的分支线,必须与接地干线相连。严禁串联连接。监理验收肘采用观察和检查安装记录。抽查设器、器具总数的10%。 ③接地体安装应符合以下规定:

位置正确、连接牢固,接地体埋没深度距地面不小于0.6m。隐敞工程记录齐全、准确。验收时采用检查隐蔽工程记录,全数检查。 ④接地(接零)线焊接搭长度规定和检验方法符合下表的规定:

接地(接零)线焊接搭接长度规定和检验方法

项 次 项 目 扁钢 l 搭接长度 圆钢 扁钢和圆钢 2 扁钢搭接焊的棱边数 规定数量 ≥2b ≥6d ≥26d 3 观察检查 尺量检查 检验方法 注:b为扁钢宽度;d为圆钢直径

⑤避雷针(网)及其支付持件安装应符合以下规定:

位置正确,固定牢靠,防腐良好;针体垂直,避雷网规格尺寸支柱不小于lOOmm,间距不大于1000mm和弯曲半径正确;固定牢靠及支持件的制作质量符合设计要求。设有标志的避雷体垂直偏差不大于顶端针杆的直径。验收时采用观察检查和实测或检查安装记录。数量为全数检查。

⑥接地(接零)线的敷设应符合以下规定:

平直、牢固,固定点间距均匀,跨越建筑物变形缝有补偿装置,穿墙有保护管,油漆防腐完整;焊接连接的焊缝平整,饱满、无明显气孔、咬肉等缺陷;螺栓连接紧密、牢固,有防松措施:防雷接地引下线的保护管固定牢靠,断线卡设置便于检测,接触面镀锌或镀锡完整,螺栓等紧固件齐全。在此基础上,防腐均匀,无污染建筑物。采用观察检查的方法进行验收。数量为全数检查。 七)电气工程竣工验收资料 1、质量控制资料

1建筑电气工程施工图设计文件和图纸会审记录及洽商记录; ○

2主要设备、器具、材料的合格证和进场检(试)验记录; ○

3设备调试记录; ○

4接地电阻、绝缘电阻测试记录; ○

5隐蔽工程验收记录; ○

6施工记录; ○

7分项、分部工程质量验收记录。 ○

2、 安全和功能检验资料

1照明全负荷试验记录; ○

2大型灯具牢固性试验记录; ○

3避雷接地电阻测试记录; ○

4线路、插座、开关接地检验记录。 ○

四、 编制依据:

1.已批准的本工程监理规划;

2.已批准的施工图纸和工程变更联系单; 3.经监理批准的施工组织设计;

4.《民用建筑电气设计规范》JGJ16-2008; 5. <<供配电系统设计规范>>GB50052-2009; 6. <<低压配电设计规范>>GB50054-95;

7. <<建筑照明设计标准>>GB50034-2004;

8.《城市道路和建筑物无障碍设计规范》JGJ 50-2001; 9.《建筑设计防火规GB 50016-2006范》GB 50016-2006; 10. <<建筑物防雷设计规范>>GB50057-2010;

11.《建筑物电子信息系统防雷技术规范》GB50343-2004; 12.<<高层民用建筑设计防火规范>>GB50045-95(2005版); 13. <<火灾自动报警系统设计规范>>GB50116-98; 14.《消防控制室通用技术要求》GA767-2008;

15.《建筑电气工程施工质量验收规范》GB 50303-2002。