目 录
一.工程概况 ·············································································································································1 二.编制依据 ·············································································································································1 三.施工部署 ·············································································································································1 四.模板结构 ·············································································································································1 五.模板施工 ·············································································································································5 六.质量要求 ···········································································································································10 七.安全文明施工 ··································································································································· 11
一.工程概况
本工程为西安市燃料总公司阿房路住宅楼,地下一层,地上二十六层,全剪力墙结构。地下室层高为 5100 ㎜,一层层高为为 4990m m,二层层高为 3600 米、三层层高为 3300 米,±0.000 以上标准层层高
为 2900 ㎜,结构楼板厚度最低为 110 ㎜,主体墙厚 200 ㎜。
二.编制依据
1、依据提供的图纸及变更文件。
2、工程遵循的标准:
(1)《工业民用建筑结构荷载规范》
(2)《钢筋混凝土结构设计规范》
(3)《钢结构设计规范》
(4)《建筑设计手册》
(5)《钢筋混凝土工程施工及验收规范》
(6)《建筑工程大模板技术规范》
三.施工部署
为保证剪力墙砼工程质量,达到清水砼标准,本工程标准层(3~
26 层)墙体砼模板采用钢质大模板,以 9~11 轴为界,分为两个施工段,交叉流水施工。
四.模板结构
1.模板结构设计
(1)模板设计参数:设计侧压力 F=60KN/㎡。
(2)模板组件材料选用:
1
a、面板选用 t =6 ㎜厚钢板,材质 Q235—A。
b、左、右、下边框选用 8#角钢,上边框选用 8 ㎜钢板,材质 Q235
—A。
c、竖肋选用 8#槽钢,材质 Q235—A。
d、横龙骨选用双 10#槽钢,材质 Q235—A。
2、模板的结构(单位为 mm):
(1)竖肋布置:竖肋布置是先以两端 225,然后再从两端往中间以间
距 n×300 布置,余数尺寸留在中间(中间余数净尺寸不得超过 300)。(2)、横龙骨布置:横龙骨用成对的 10#槽钢背对背布置四道在竖肋上,两槽钢之间留有对拉螺栓孔位置,其尺寸等于 55 ㎜。横龙骨两端开有 20×40 长孔,其用途是为了安装模板连接板,以此加强模板
刚度和控制模板拼缝间的错台量。竖向间距从下往上布置,间距为300、650、750、900、300。
(3)边框布置:上、下边框连接孔为(150,300,n,300,150), 2900 高模板左、右边框连接孔(50,100,150×8,200,150×8,100,50),其它梁下插板边框连接孔自下而上为 140,150×8,200,150×n。
3、模板的选型
(1)、模板高度的选用:本工程标准层层高为 2900 ㎜,楼板厚 100
㎜,但考虑到模板的通用性,外墙墙体门窗洞口完全镜像对称分布,
流水时整墙模板不能平移流水,只能镜像流水。模板每次进行流水时
需重新组拼,这样给施工带来很不便。因此外墙墙体模板制作高度同
内墙 2850 ㎜,同时不考虑装饰带,这样可以避免重新组拼现象的发
2
生。模板的型式详见立面图。
(2)考虑到模板在运输及吊装的问题,模板最大单元板宽度为 2400
㎜。
4、角模的结构
(1)角模的种类:阳角角模、可调阴角角模、固定阴角角模。
5、墙体垂直高度方向处理
内墙模板高度均按 2850 ㎜设计,内墙浇捣高出板底标高 10~15
㎜处,然后周围布置上延模板(H=200)与顶板一同浇捣,浇捣完毕
后,外墙模板吊至上延模板上,进行二次支模。
6、内墙模板高 2850 ㎜,能保证内墙浇筑高度高出板底标高 15 ㎜,
在浇注顶板时,墙壁面与顶板处用木方加竹胶板顶紧,可保证墙面与
顶板接茬线为清角,无错台。
7、模板均按墙的实际尺寸配置。
8、支腿、走台及附件数量配置根据模板宽度设置一个或多个。走台
设置时,只考虑一侧墙体就行。支腿、走台布置数量为小于 2.1m 布
置 1 个,2~4m 布置二个,4~6m 按三个考虑。
9、角部处理:
(1)阴角模:内外墙阴角模均为可调型式,外墙阴角模均为平口型
式。阳角模边框与模板边框连接为平口,其模板高度为相邻模板高度
一致,外墙平面模板、角模在阳台、空调板位置时,按外墙处理。
本工程选用一种规格的阴角模,局部采用不对称角模,墙体厚度
200 ㎜进行计算,阴角模与大模板采用搭接方式,正常使用时,由于
3
搭接处留有 3~5 ㎜间隙,会产生相应的凸台,施工时,应随拆模随
用扁铲剔平;为了防止角模向内倾斜,应用钩头螺栓钩住角模,拉结
在大模板上。当角模大于 300 或窗口断开时,角模上设有穿墙孔位,
防止胀模。
10、阳角模:尺寸一般情况下均为 400×400 ㎜,角模与大模板采用
螺栓连接的方式,并带有龙骨,角模与平面模板之间用模板连接板连
接,防止胀模,加强角部的刚度。
11、对拉螺栓部位处理:本工程仍选用我们目前使用的带锥度的螺栓,
拆模时只需从一端轻打螺杆,就很容易退出。不需使用塑料套管,即
节省了人力,又节省了物力。
12、本工程的设计的难点在于剪力墙与门窗接合部位处理,仍采用“断
窗断口”型式,即门窗洞口及边梁均断开处理方式进行配板,这样可
以保证模板拼接平整和漏浆问题以及常见门窗移位、跑模、不直等缺
陷。
13、梁墙结合处及梁板交接处的处理:在墙体中间与梁交界处,梁截
面较小时,为保证模板的流水通用性,采用预埋梁窝的方法,即在梁
窝部位先填充泡沫砖,在梁的外侧用钢丝网包严,防止漏浆,在墙砼
浇捣、模板拆除完毕后,再在梁的位置绑筋。梁截面尺寸较大时,将
此处模板断开,按通常剪力墙情况来配板。墙末端与梁交界处的处理
方法同上。
14、飘窗、空调板、窗套部位的处理:三者钢筋预埋,砼与墙体分开
浇筑。待拆模后将预埋钢筋外部砼錾开,将钢筋扳出,再进行其它工
4
序。
丁字墙部位处理:本工程丁字墙处理采用补板型式,为防止涨模,
模板与模板之间采用模板连接板加强拼接处刚度。
16、高低板处理:阳台板面标高比结构板面标高高 60mm,此处低板
须吊模,外墙丁字墙部位改变插板边框连接孔,阳角部位改变阳角边
框连接孔,另在上下龙骨间用小背楞和钩头螺栓与相连两块模板的竖
肋连接紧固。(特殊部位现场改制)。
五.模板施工
1.施工准备
(1)熟悉模板结构和模板平面布置图。
(2)安排好大模板堆放场地,并把大模板的堆放场地平整好,在平
地上面垫木方加钢管操平。由于大模板体积大,重量大,应该放在塔
式起重机半径范围之内,以便于垂直吊运。
(3)模板进现场后,应依据配板设计要求清点数量,核对型号。
(4)依据模板平面布置图做出模板组拼明细表,应注明其编号、单
元模板(按从背面自左向右的顺序)、梁侧模(注明标高)及龙骨的
型号,组拼后用醒目字体对模板进行编号。
(5)模板按组拼明细表组拼后,要用扁铲、出锈机进行清渣、出锈,
擦去表面油污,板面拼缝处要用环氧树脂腻子嵌缝,然后涂刷脱模剂。
2.模板安装
(1)安装前应进行施工技术交底,要有针对性、指导性和可操作性。
(2)大模板安装前,应在钢筋隐蔽工程验收完毕后,弹好模板内侧
5
线及外侧控制线,门边线及标高线,将楼面清理干净,检查墙体中心 线、边线、模板安装控制线,并检查钢筋网片固定情况,电线管、电
线盒与钢筋或大模板固定情况。门窗内部安装好,凡与砼相接触的预
埋件,其表面均应刷涂脱模剂或亮机油,门窗模的侧面与模板相接触
处也相应要粘上海绵条。
(3)墙体钢筋阴角处,应焊好“工”字形定位筋,其间距不能大于
300 ㎜,防止角模的位移。
(4)涂刷脱模剂或亮机油:在模板、阴、阳角模、门窗堵板等表面
上刷涂脱模剂或亮机油,要涂刷均匀,不得漏涂且不能刷得太厚,便
易于脱模,并不易锈蚀。刷过隔离剂的模板遇雨淋或其它因素失效后
必须补刷。在楼面上涂刷隔离剂时,应先在楼面上垫好养护毛毡,防
止隔离剂污染楼面。使用的隔离剂不得影响结构工程及装修工程质
量。穿墙螺栓每周转一次,都得涂抹黄油,并涂抹均匀,便于螺栓每
次好拆。
(5)在大模板下部抹好找平层砂浆,依据放线位置将模板吊到在模
板平面布置的位置。
(6)安装支撑架、三角支架等附件,其安装数量根据模板宽度设置
一个或多个。走台设置时,只考虑一侧墙体就行。支腿、走台布置数
量为小 2.1m 布置 1 个, 4~6m 布置三个计算。
(7)安装模板顺序:按先横墙后纵墙原则,再用撬棍移动模板到墙
位线上。用支撑架调节模板的垂直度,旋紧穿墙螺栓。安装一间,固
定一间。
6
(8)纵横墙壁交接处,模板安装顺序为先立阴角模,底部需粘贴海
绵条,并给临时固定,再支模板。
(9)模板安装就位后,检查模板拼缝处是否严密,竖向边框是否垂
直,为防止漏浆。底部若有空隙,应用海绵或橡胶条塞严,但不可将
其塞入墙体内,以免影响墙体的断面尺寸,检查合格后,才能浇注砼。
(10)平面模板之间连接时,先将两块模板对接处边框孔位边缘对齐,
上、中、下用三个 M16×40 螺栓预紧,然后把模板连接板放入横龙
骨中,在其中一块模板横龙骨的第四孔位插入另一模板横龙骨的第一
孔位中,用锤子向下敲打楔板(扁销),使模板之间达到紧密相连,
而后分别将楔板(扁销)插入到各龙骨的第四孔和第一孔最后再把边
框上孔位用螺栓全部拧紧。
(11)平面模板与角部模板连接时,将模板就位后,每个企口阴角处
用三个阴角连接器分别安装在相应位置处,拧紧螺栓就可。平口角模
处在模板边框与角模边框孔位上安装螺栓拧紧。
(12)砼浇筑进程中,应有有关人员进行监视,发现问题应及时解决
或汇报。
(13)为避免浇筑砼时,因墙模高而产生离析现象,浇筑层高度不超
过 300mm。布料设备的出口离模板内侧面不应小于 50mm,且不得向模板内侧面直冲布料,因浇筑砼时下料高度较高,对模板的侧压力过大,造成胀模。并在下料时,应避免在墙体中间下料,尽量在墙体的交接处进行下料,下料速度不宜过快,应均匀进行。
(14)浇注砼时必须按照有关规定和规范进行施工。
7
3.模板拆卸
(1)大模板的拆除应根据 JGJ74—2003《建筑工程大模板技术规程》
条文 6.5.1 要求进行。拆除时应能保证砼表面及棱角不受损坏,不粘
模。一般情况下,当墙体砼强度达到 1N/㎜ 以上时,方可拆除大模 板。但在冬季施工时应视冬季施工方法和砼强度增长情况决定拆模时
2
间。门窗洞口底模拆模原则是先浇先拆,后浇后拆,与浇注顺序一致。
单块大模板拆除顺序,先拆平面模板,后拆角模。
(2)每块大模板的拆除顺序是:应先将穿墙螺栓等连接件拆除,再
松动支撑架的地脚螺栓,使模板与墙面脱离。当局部地方有吸附时,
可在模板下部用撬杆松动,但不得在墙上晃动或用大铁锤进行敲砸。
拆下的附件应及时进行清理,放入工具箱中,以便周转使用。
(3)穿墙螺栓的正确拆除方法是:当要拆除大模板时,先松动并拆
除楔板,同时将另一方向螺母向里紧两扣,使螺杆与混凝土界面脱开,
然后可将穿墙栓轻轻卸下,切不可用铁锤敲打,以免螺杆拆弯。大模
板拆除穿墙螺栓前,顶部与钢筋用铁丝做适当的连接,防止大模板脱
模后突然倾倒。
(4)角模的拆除:由于角模的两侧都是混凝土,吸附力较大,因而
当拆除平面大模板时应立刻松动角模,使角模与混凝土界面分开。若
时间过长会造成角部模板拆除困难,因而在拆除角模时应注意其拆模
时间,不要太长。当拆模较困难时,可先将模板外表面的砼清除,然
后再用撬棍在模板下部撬动,但不得在墙上晃动或用大铁锤进行敲
砸。角模拆除后,凸出部分的砼应及时进行剔除,凹口部位应及时用
8
等标高砂浆修补。
(5)脱模后在起吊大模板前,要认真检查穿墙螺栓等附件是否全部
拆完,与其它模板有勾、挂、兜、绊的地方,同时应检查模板吊环的
焊缝是否焊牢,有无裂纹,起吊时,吊环应落在模板重心部位,并应
垂直缓慢提升无障碍后,方可吊出,吊运时不得碰撞墙体。大模板起
吊前,还应检查吊用绳索、卡具及每块模板上的吊钩是否牢靠,然后
将吊钩挂好,解除一切约束,稳起稳吊。
(6)大模板落地或周转至另一工作面时,必须一次安放稳固,倾斜
角在 75~80。模板及其配件拆除后,应及时将模板上的混凝土及水 泥浆用扁铲或钢丝刷、砂纸进行清除干净且刷好脱模剂以备下次使
0
用。在楼层上涂刷脱模剂时,要防止将脱模剂溅到钢筋上和污染楼面。
(7)大模板放置时,上面不得压有电线和气焊管线。
4.模板的保养
(1)大模板进场后,穿墙螺栓和地脚螺栓等应刷好机油。零配件入
库保存时,应分类存放。
(2)模板面板正面必需刷好脱模剂。脱模后应将模板板灰渣清理干
净,涂刷脱模剂后待用。
(3)在使用过程中应避免碰撞,防止模板倾覆。
(4)模板多次使用后检查有无过大变形及损坏,并及时维修。
模板在使用过程中的改制,在使用完毕后需及时修复。
(5)对暂不使用的大模板拆除支架维修后,板面应进行防锈处理,
板面向下分类码放。
9
(6)大模板叠层堆放时,在模板的底部及层间应加垫木,垫木应上
下对齐,垫点应保证模板不产生弯曲变形;叠放高度不宜超过 2m,
当有加固措施时可适当增加高度。
六.质量要求
1.制作质量标准 项目 质量标准 检测工具与方法 (一)制作质量 1、平面尺寸 0~-2 钢卷尺测量 2 米靠尺,塞尺测量 2、板面平整度 ≤2 ㎜ 3、对角线长 3 ㎜ 钢卷尺测量 放置在平台上,对角拉线用直尺检查 4、模板翘曲 1/1000 5、孔眼位置 +2 ㎜ 钢卷尺测量 拉线用直尺检测 6、模板边平直 2 ㎜
2.大模板安装质量标准 序 项目名称 号 允许偏差 检测方法 1 每层垂直度 3 ㎜ 用 2 米托线板 尺量 2 位置 2 ㎜ 2 ㎜ 3 上口宽度 标高 尺量 拉线和尺量 4 5 ㎜ 2 ㎜ 5 表面平整度 用 2 米靠尺或楔形塞尺 尺量 6 墙轴线位移 预留管,预留孔中心线 7 位移 3 ㎜ 3 ㎜ 拉线和尺量 8 预留洞中心线位移 10 ㎜ 拉线和尺量 拉线和尺量 9 预留洞截面内部尺寸 10 10 ㎜ 1.5 ㎜ 模板接缝宽度 拉线和尺量 拉线和尺量 11 预埋钢板中心线位移 3 ㎜
3.常见质量问题与防止措施
序 质量总题 号 防止措施 1 内墙墙底砼烂根 模板底部缝隙处加设木条或粘贴海绵条,防止漏桨和烂根现 10
象发生。 墙体钢筋移位外露 采用塑料卡环进行保护和定位,或使用定位钢筋撑 2 3 墙体垂直度偏差或不平度 超差 墙厚不一致 模板变形,应进行修复;支模时应加强坠吊检查。 4 采用定位钢筋分布在墙体钢筋内,支模时顶要大模板的竖肋 位置 5 阴角不垂直、不方正 检查角模是否变形,变形应及时进行修复。阴角两侧粘贴海 绵条。 检查角模是否变形,变形应及时性进行修复。 6 阳角不垂直 梁柱接头处漏 7 柱模尺寸采用负偏差,模板上部加设凸条,砼浇注后粘贴每 绵条。 脱模剂涂刷均匀,完整;脱模时间过早,砼强度达到 1MPA 方可拆模。 8 砼脱模粘连
七.安全文明施工
1、进入施工现场必须戴安全帽并系好帽带,高空或临边作业必须佩
戴安全带,并应系牢高挂低用。
2、施工时禁止穿高跟鞋、硬底鞋、拖鞋、严禁赤膊干活,严禁酒后
上班,不准吸烟。
3、操作前必须先检查外架、天井等临边防护是否合格,不合格不能
施工。
4、结构施工中,必须搭设防护网和安全网,防护网要随层升,并高
出作业面 1m。
5、大模板存放场地必须平整夯实,不得存放在松土和凸凹不平的地
方,雨季施工不得积水,存放大模板处严禁人员逗留,存放按施工总
平面图分区存放。
6、当风力达 5 级时(含 5 级),应停止吊装。
7、大模板走台严禁安放在外墙外侧模板上,即严禁人员从外墙外侧
模板上通过。
11
8、模板施工前,必须进行安全技术交底。
9、模板施工应设专人指挥,统一信号,密切配合,信号指挥工和挂
钩人员,必须在安全可靠的地方才可以操作,严禁人随模板一起吊运。
10、所有模板配件拆除完毕后,方可将模板吊走,杜绝冒险蛮干作业,
垂直吊运必须采取两个以上的吊点,方可将模板吊走,不充许一次吊
运二块及以上模板。
11、支拆模板应按顺序进行,模板及支撑在固定前,禁止攀登,不准
在拆除的模板上操作,支撑架各连接须扣紧,勿遗漏,使用中应经常
检查支撑架有无拆改、松扣、脱钩现象,发现问题及时整改。
扶风县建筑总公司西安燃料总公司阿房路住宅楼项目部
二 0 一三年三月一日
12